Argues that the AI-driven data centre boom risks higher climate pollution, power prices and water demand, and that enforceable national standards applying to new and existing facilities could instead support clean energy. Makes twelve recommendations on renewable matching, fossil fuel, efficiency, water, reporting, costs, communities and workforce.
Key points
Quotes are the submitter’s own words. Text taken from documents, including scanned pages read by text-recognition software, can differ from the PDF. Check the original. Listed in the same order as on the submission’s page in the interactive guide.
States, citing Australian Government projections, that the AI-driven data centre boom is putting progress on cutting climate pollution at risk.
But the Australian Government’s own projections show that the data centre boom – driven by the rapid growth of AI and the international technology companies building it – is putting this progress at risk.
Argues the renewable obligation should cover every data centre of at least 30 MW from 23 March 2026, with a fair, time-limited transition for existing facilities and contracts.
The renewable obligation should be phased in for every data centre in Australia of 30 MW or more, from 23 March 2026, with a fair, time-limited transition for existing facilities and contracts.
Argues that new renewable supply backing a data centre should be built within three years of operations, with material financial penalties for non-compliance.
The new generation supported by a data centre should be built within three years of starting operations. Mechanisms should incentivise the capacity to be built as quickly as possible, with material financial penalties for non-compliance at the end of the three-year window.
Argues that data centres should not be permitted to use potable water for cooling in water-stressed regions.
In water-stressed regions, data centres should not be permitted to use potable water for cooling – without exception.
Argues that data centres in suitable regional locations could support economic development, with low environmental impact and without additional strain on water resources.
This is not about shifting impacts from metropolitan areas into regional communities, but about identifying locations where data centres can support economic development, make productive use of existing infrastructure, and support the shift to clean energy, with low environmental impact and without putting additional strain on water resources.
Argues, citing the ETU, that data centres could exacerbate electrician shortages, leaving Australia short of around 70,000 licensed electricians by 2030.
Without action, data centres will exacerbate existing skills shortages, and could leave Australia short of around 70,000 licensed electricians by 2030 (ETU 2026).
Recommendations
Recommendations are shown beside the submission’s own words. Listed in the same order as on its page in the interactive guide.
Before introducing standards into Parliament, close gaps on climate-target alignment, commencement and application, defining new renewables and ruling out off-grid gas as a primary power source.
The need to align the industry’s growth with climate targets is not mentioned in the Government’s recent consultation paper; the start date and approach to the application of the standards is not confirmed; there is no clear definition of what counts as "new" renewables; and off-grid gas is not explicitly ruled out as a primary power source. These gaps must be closed before the standards are introduced into Parliament, and we urge the Committee to recommend that the Government does so.
Require operators to disclose tenants to governments and utilities during planning and grid connection, show how both parties will meet the requirements, and pass obligations on through tenancy agreements.
Operators should be required to disclose their tenants to governments and utilities during planning and grid connection, show how both parties will meet the requirements, and pass obligations on to customers through tenancy agreements.
Phase national standards and the renewable obligation into all data centres with total energy demand ≥30 MW and their customers, with time-limited transitional provisions depending on when facilities began operating.
The national standards, including the renewable obligation, should be phased in for every data centre with a total energy demand of 30 MW or greater – both new and existing – and its customers. The threshold should be assessed across portfolios, staged developments and co-located facilities, so projects cannot be split to avoid it. This would include transitional provisions that give facilities a time-limited grace period, depending on when they began operating:
Assess the 30 MW threshold across portfolios, staged developments and co-located facilities so projects cannot be split to avoid it.
The threshold should be assessed across portfolios, staged developments and co-located facilities, so projects cannot be split to avoid it.
Require any facility that commences operations after 23 March 2026 to contract new renewable generation and storage immediately and have new capacity operating within three years of starting operations.
Any facility that commences operations after 23 March 2026 should contract new renewable generation and storage immediately, and have new capacity operating within three years of starting operations.
Consider reasonable transitional arrangements for data centres entering power agreements before the legislation commences.
Reasonable transitional arrangements for data centres entering into power agreements before the commencement of the legislation should be considered.
Have existing facilities transition when their current power agreements end, following the same three-year path.
Existing facilities should transition when their current power agreements end, following the same three-year path.
Define 'new' renewables as generation and storage that has not reached final investment decision when the agreement is signed.
“new” should be defined as generation and storage that has not reached final investment decision (FID) when the agreement is signed.
Do not treat projects awarded government underwriting (such as through the Capacity Investment Scheme or LTESAs) as 'new'.
Projects that have been awarded government underwriting (including through Capacity Investment Scheme (CIS) or NSW’s Long-Term Energy Service Agreements (LTESA)) should not be treated as "new".
Underpin the renewable obligation with long-term PPAs with new projects and/or on-site renewable generation, require agreements of at least ten years, and surrender new-project REGOs for every MWh consumed.
Long-term PPAs with new projects (and/or on-site renewable generation) should therefore underpin the renewable obligation for data centres, with ongoing compliance through the surrender of REGOs from new projects for every MWh a data centre consumes. Like NSW’s requirements, agreements should have a duration of at least ten years.
Time-match REGOs to electricity use.
REGOs should be time-matched to electricity use, to ensure that data centre electricity use aligns with where and when renewable energy is actually being generated or discharged
Design renewable-energy and storage procurement requirements to avoid undermining long-term PPAs; consider state-based portfolio demand matching, particularly for smaller facilities.
Mechanisms to require renewable energy and storage procurement should be carefully designed to ensure that there are no unintended consequences that could undermine this ability. For example, a state-based portfolio approach to demand-matching may be appropriate, particularly for smaller facilities.
Require data centres and customers with total demand ≥30 MW to contract pre-FID renewable generation matching at least 100% of demand before operations begin.
Data centres and their customers with total energy demand of 30 MW or greater must be required to enter into long-term contracts, such as power purchase agreements (PPAs), with pre-FID renewable generation projects to match no less than 100% of their demand, before they can commence operations.
Demonstrate ongoing compliance through surrender of time-matched REGO certificates from new projects for every MWh consumed, with the Clean Energy Regulator responsible for compliance.
Ongoing compliance should be demonstrated through the surrender of time-matched Renewable Electricity Guarantee of Origin (REGO) certificates from new projects for every MWh consumed. The Clean Energy Regulator should be responsible for compliance.
Require pre-operation demonstration of contracted pre-FID capacity to the CER and proof of construction within three years; impose material penalties unless delays are demonstrated to be wholly outside the data centre's control.
A new data centre should have to demonstrate to the Clean Energy Regulator (CER) that it has contracted with new (pre-FID) renewable capacity before it can commence operations. It must then demonstrate that this supply has been built within three years of the data centre starting operations. There must be material financial penalties for non-compliance after this time, unless a data centre can demonstrate the delays are wholly outside its control.
Adequately resource the Clean Energy Regulator to perform the additional compliance responsibilities.
The CER must be adequately resourced to perform these additional responsibilities to the high standard the community rightly expects.
Require a data centre to match its actual energy use with new renewable generation, with the volume of new renewable electricity procured increasing over time in line with actual demand.
A data centre should be required to match its actual energy use with new renewable generation, meaning the volume of new renewable electricity procured should increase over time in line with actual data centre demand.
If REGOs from existing projects are used as an interim measure, limit them to recently built projects and require data centres to make up any shortfall by surrendering REGOs from new projects once built.
If REGOs are used in the interim, they should be limited to recently built projects, and data centres should have to make up any shortfall by surrendering additional REGOs from their new projects once built
Accelerate renewable projects through earlier FID support including finance, easing supply-chain and labour pressures, and faster approvals including priority access to the investor Front Door.
The Government should also speed up the delivery of new renewable projects, for example by supporting renewable projects to take FID earlier (including through the provision of finance), through policies to alleviate supply chain and labour force pressures and by achieving faster approvals, including by giving renewable projects priority access to the Government’s investor Front Door.
Require data centres to contract with, or install, new firming capacity that is in the grid from day one of operations.
Data centres must be required to contract with (or install) new firming capacity that is in the grid from day one of operations.
Rule out off-grid or behind-the-meter fossil fuel generation as a primary power source at any time, including while new renewable supply is being built.
Data centres must not be permitted to rely on off-grid or behind-the-meter fossil fuel generation as a primary power source at any time, including while new renewable supply is being built.
Set national baseline energy and water efficiency metrics for data centres.
The Commonwealth should set national baseline energy and water efficiency metrics for data centres.
Require all data centres above 30 MW to demonstrate a design PUE of no greater than 1.34 before they are approved.
All data centres above 30 MW should be required to demonstrate they will achieve a design PUE of no greater than 1.34 before they are approved.
Require data centres above 30 MW to maintain a minimum five-star NABERS Energy rating once operating.
All data centres above 30 MW should be required to demonstrate they will achieve a design PUE of no greater than 1.34 before they are approved. They should be required to maintain a minimum five-star NABERS Energy rating once operating.
Regularly review and progressively strengthen efficiency benchmarks to reflect technological advancement and best practice.
All data centres above 30 MW should be required to demonstrate they will achieve a design PUE of no greater than 1.34 before they are approved. They should be required to maintain a minimum five-star NABERS Energy rating once operating. These benchmarks should be regularly reviewed and progressively strengthened to reflect technological advancements and evolving industry and international best practice.
Prioritise load shifting wherever possible, for example scheduling non-critical computing tasks during high renewable output.
Wherever possible, flexibility should be achieved through load-shifting, for example by scheduling non-critical computing tasks for times of high renewable output.
Apply flexibility requirements to both operators and their customers.
Flexibility requirements should therefore apply to both operators and their customers.
Limit fossil diesel to backup in grid emergencies; prohibit its use for demand response or avoiding high electricity prices.
Fossil diesel generation must therefore be limited to providing backup power in grid emergencies. It should not be used for demand response or to avoid periods of high electricity prices.
Require data centres and customers to demonstrate grid-demand reductions ≥25% of forecast average load for up to two hours during peak/system-stress events, using load shifting, batteries and on-site renewables rather than diesel.
Data centres and their customers should be required to demonstrate the ability to reduce grid demand by at least 25% of forecast average load for up to two hours during peak and system stress events, consistent with NSW's Data Centre Guidelines. This flexibility should be delivered through load shifting, battery storage and on-site renewables rather than diesel.
Limit diesel backup to grid emergencies, with a pathway to lower-emissions backup, and exclude data centre backup generation from the fuel tax credit scheme.
Diesel backup generation should be limited to grid emergencies, with a pathway to lower-emissions backup such as batteries and renewable diesel. Data centre backup generation should also be excluded from the fuel tax credit scheme.
Prohibit data centres from using potable water for cooling in water-stressed regions, without exception.
In water-stressed regions, data centres should not be permitted to use potable water for cooling – without exception.
Elsewhere, require water-intensive cooling or facilities exceeding a set annual water volume to use recycled/non-potable water; allow potable water only as a time-limited last resort with a transition plan and full same-catchment offsets.
In other parts of the country, facilities using water-intensive cooling, or exceeding a set annual water volume, should also be required to use recycled or non-potable water – with potable water a time-limited last resort that is covered by a plan to transition to non-potable or recycled water, and fully offset within the same catchment.
For data centres ≥30 MW, require approval-stage WUE ≤1.0 for potable water and ≤1.6 for non-potable water, no weaker than NSW/Victoria, with annual reporting of actual WUE and water use.
All data centres of 30 MW or more should meet a design WUE target at approval, no weaker than Victoria's and NSW's (1.0 or lower for potable water, 1.6 or lower for non-potable), and report actual WUE and water use annually.
Require a minimum NABERS water rating once developed.
A minimum NABERS water rating should be required once developed.
Require annual, public, nationally consistent reporting of energy use, efficiency, climate pollution and water use by data centres and customers.
Data centres and their customers should report energy use, efficiency, climate pollution and water use annually and publicly, in a nationally consistent format.
Have all levels of government and industry develop a nationally consistent reporting framework balancing commercial sensitivity and security with best-practice reporting standards.
The wide variation between industry and institutional demand forecasts (Climate Council 2026c) also shows there is a need for governments at all levels, and industry, to work together to develop a nationally consistent framework that balances commercial sensitivity and security considerations with best practice reporting standards.
Require nationally consistent operator/customer reporting of electricity use/source, PUE, backup generators, emissions, REGO retirement, water use/source, water/energy efficiency, drought resilience and local water-resource impacts.
Set up a framework for nationally consistent reporting for both data centre operators and customers, including – but not limited to: electricity use, electricity source, PUE, backup generator use, greenhouse gas emissions, retirement of REGO certificates, water use and source, water and energy efficiency measures, drought resilience measures, and impacts on local water resources.
Develop a consistent approach to forecasting so governments, regulators and utilities can better coordinate and plan for data centre development.
As part of this, a consistent approach to forecasting should be developed to allow governments, regulators and utilities to better coordinate and plan for data centre development.
Review cost recovery frameworks and amend as required so the industry, rather than homes and businesses, bears water and energy network upgrade costs for data centre demand.
Cost recovery frameworks must be reviewed and amended as required to ensure the industry, rather than homes and businesses, absorbs the costs associated with water and energy network upgrades needed to service data centre demand.
Require community and First Nations engagement, including free, prior and informed consent, transparency, benefit sharing and environmental protection.
The expansion of Australia’s data centre industry must be underpinned by robust frameworks for community engagement, transparency, benefit sharing and environmental protection. Development should avoid areas of high biodiversity value, protect water resources and cultural heritage. It is essential that any such approach is underpinned by robust frameworks for community and First Nations engagement – including the principles of free, prior and informed consent – along with transparency, benefit sharing, and environmental protection.
Avoid data centre development in areas of high biodiversity value and protect water resources and cultural heritage.
Development should avoid areas of high biodiversity value, protect water resources and cultural heritage.
Coordinate and promote data centre development in suitable regions with existing energy infrastructure and sufficient water resources.
Government coordination could identify and promote development in suitable regions with existing energy infrastructure and sufficient water resources.
Consider prioritised approvals and connections in suitable regions with existing energy infrastructure and sufficient water, ensuring all environmental, planning and community requirements are fully met.
Government coordination could identify and promote development in suitable regions with existing energy infrastructure and sufficient water resources. For example, prioritised approvals and connection processes could be offered, while still ensuring all environmental, planning and community requirements are fully met.
Consider requiring that only renewable developers signed on to the Developer Rating Scheme are eligible to supply data centres.
The Government could consider a requirement that only renewable developers that have signed on to the Developer Rating Scheme are eligible to supply data centres.
Also require related energy projects to take on apprentice quotas during construction and pay levies expanding training capacity.
Climate Council supports the ETU’s recommendation that data centres and related energy projects should be required to take on a quota of apprentices in their build, and pay a levy to expand training capacity.
Require new data centres above 30 MW to take on an apprentice quota during construction and pay a training levy.
New data centres above the 30 MW threshold should be required to take on a quota of apprentices during construction and to pay a levy to expand training capacity